EXPRESSWAYS
TO
THE NEW
AIRPORT OF HONG KONG
In October 1989, the then
government of Hong Kong decided to build the new airport at Chek Lap Kok to
replace the original Kai Tak International Airport. Together with other associated projects, they were placed
under an ¡§Airport Core Programme (ACP)¡¨.
The target was to have all the ACP projects completed by year 1997. Below shows a layout of this ambitious
programme.
|
|
The Kai Tak Airport had been in
operation since 1936. To meet the
fast growing air traffic, it had undergone six stages of major expansion. The last stage was actually carried out
in parallel with the development works for the new airport. In year 1994, upon completion of the
last stage of expansion, Kai Tak Airport had a design capacity of handling 24
million passengers per annum. In
actual fact, through management means, the use of the Kai Tak Airport was
stretched beyond its limit to handle 29.5 million passengers per annum in year
1996.
|
|
|
Kai
Tak Airport |
Kai Tak Airport, which was situated
within the urban area, could not undergo any further major expansion to meet
the ever-increasing air traffic, and the need for a replacement airport was
obvious. A new airport would bring
about other social and economic benefits.
The benefits to be derived from the new airport are summarized below:-
A new
international airport operatable around-the-clock and an environment free of
aircraft noise for 380,000 people living under the Kai Tak flight path
As Kai Tak was situated in the
urban area, there were 380,000 people living directly under its flight
path. Hence the operation of Kai
Tak had to be suspended daily from mid-night to early morning to avoid causing
them intolerable nuisance. After
moving to Chek Lap Kok, such problems could be overcome and hence the new
airport could operate around-the-clock.
34
kilometres of new highways and railway to provide a high-speed link between the
urban area and the airport
Since
Chek Lap Kok is situated at the originally undeveloped northern shore of the
Lantau Island, a new road and rail link was required in order to provide
high-speed link with the urban area.
Such high-speed link would have been impossible for the Kai Tak Airport,
which is surrounded by already saturated road network. The roads to the new airport also added
capacity to the overall road network, thus relieving capacity problems in some
congested areas.
A
third cross-harbour road tunnel
Along
the road link to the new airport is the badly needed third cross-harbour road
tunnel connecting Hong Kong Island with Kowloon. This provided the immediately required extra capacity to
relieve the acute situation of the two existing heavily over-loaded cross-harbour
tunnels.
The
world¡¦s longest road-rail suspension bridge, forming part of the first road
link to Lantau Island
Along
this new road link to the airport is the Lantau Link, which in fact is the
first road link to connect Lantau Island, the largest island of Hong Kong, with
the urban area. On the Lantau Link
is a suspension bridge, the Tsing Ma Bridge, which is the world¡¦s longest
road-rail suspension bridge.
Hong
Kong¡¦s ninth new town at Tung Chung on north Lantau
The
first new road access to the Lantau Island also opened up the opportunity to
develop this large outlying island.
The Tung Chung new town is a new town immediately next to the Chek Lap
Kok Airport.
Two
major reclamations in West Kowloon and Central District, and the possibility to
redevelop the replaced Kai Tak Airport
Furthermore,
in order to build the new road and rail link, there were two major reclamations
required. The land obtained,
together with the land released after closing the Kai Tak Airport, provided
cure to solve the acute land shortage problem of Hong Kong.
AIRPORT ECONOMICS
The best way
to express the benefits derivable from the new airport is perhaps in terms of
dollars. An economic appraisal
study was conducted in year 1989 covering only those costs and benefits associated
with the new airport and its associated projects which could be readily
expressed in monetary terms, including:-
Capital
costs
Operating
costs
Transport
user and road accident costs
Disadvantages
to Hong Kong of not being able to cater for the projected air passenger traffic
After
deducting the costs, it was estimated that by year 2006, a total of HK$27 to
HK$56 billion (in 1988 prices and 1US$=7.8HK$) net benefit could be obtainable
by building the new airport.
EXPRESSWAYS
TO THE NEW AIRPORT
As said new roads were included
under the ACP to serve the new airport.
Other than these, two major projects that connect the ACP road network
with the northwest New Territories, Ting Kau Bridge and the Route 3 (Country
Park Section), were implemented independently of the ACP. The function of the two added roads is
to provide a high speed, direct access between the northwest New Territories
with the new airport as well as the urban area.
Since the 45km expressways to the
new airport was an enormous piece of infrastructure development work, it had to
be divided into quite a number of smaller, manageable projects, namely the
Western Harbour Crossing, West Kowloon Expressway, Route 3 (Kwai Chung &
Tsing Yi Sections), Lantau Link comprising the Tsing Ma Bridge and the Kap Shui
Mun Bridge, North Lantau Expressway, Ting Kau Bridge and the Route 3 (Country
Park Section). All these projects
are highlighted and shown in the plan below.
The cost to implement the various
expressway projects are listed in the table below:
|
Project |
Cost (HK$ billion in money of the day/outturn
prices) |
|
Western
Harbour Crossing |
6.0 |
|
West
Kowloon Expressway |
3.1 |
|
Route 3
(Kwai Chung & Tsing Yi Sections) |
4.1 |
|
Lantau
Link |
11.0 |
|
North
Lantau Expressway |
7.8 |
|
Ting Kau
Bridge |
1.7 |
|
Route 3
(Country Park Section) |
7.3 |
|
Total |
41.0 |
Basically the funds came from public
money. However, where possible,
funds from private sources were utilized.
Two of the projects, Western Harbour Crossing and the Route 3 (Country
Park Section), were employing this strategy. Essentially these two projects were built under a
Build-Operate-Transfer (BOT) arrangement.
Through BOT, the funding for the construction came from private companies,
who own the completed works, and earn returns by imposing car tolls. The operation of the roads built under
BOT will last for a period of 30 years, after which the ownership as well as
the operation of the roads will have to be handed back to the government.
DESIGN AND CONSTRUCTION HIGHLIGHTS
Along the expressways to the new
airport, the most spectacular features are the three big bridges. The Tsing Ma Bridge connects Tsing Yi
with Ma Wan, Kap Shui Mun Bridge continues from Ma Wan to Lantau Island, while
the Ting Kau Bridge goes in the northward direction and connects Tsing Yi with
Ting Kau.
Both Ting Kau and Kap Shui Mun
bridges are cable-stayed bridges.
Kap Shui Mun Bridge has two towers with a span of 430 metres in between,
while Ting Kau Bridge has three towers, spacing at 448 metres and 475 metres
apart. The total length of the
Ting Kau Bridge is 1,177 metres, making it the longest three tower cable-stayed
bridge in the world. On the other
hand, Tsing Ma Bridge is a suspension bridge, which, like the Kap Shui Mun
Bridge, forms part of the Lantau Link.
Tsing Ma Bridge is a road-rail combined bridge. On the top deck is a dual 3-lane
carriageway, while the lower deck provides an extra lane for emergency purpose,
as well as room for accommodation of the railway to the new airport. The suspension bridge has a main span
of 1,377 metres, making it the world¡¦s longest road-rail suspension
bridge. Below is a photo showing
these three bridges.
|
|
|
The
Tsing Ma Bridge, Kap Shui Mun Bridge and Ting Kau Bridge |
Another major component are the
tunnels. Along these expressways
there are three tunnels. All these
tunnels are dual 3-lane tunnels, which are the first of their kind in Hong
Kong. Two are bore tunnels. One of the tunnel forms part of the
Route 3 (Country Park Section), while the other forms part of the Route 3 (Kwai
Chung & Tsing Yi Sections).
The third tunnel, the Western Harbour Crossing, is however formed by
submersed tubes. Typical sections
of the bore tunnels and submersed tubes are shown below.
|
|
|
Typical Section of Submersed Tubes |
|
|
|
|
|
Typical
Section of Bored Tunnel |
Other than the bridges and tunnels
are the roads, either on viaducts or at-grade. Along the North Lantau Expressway is a long stretch of
mostly at-grade road measuring 12.5km long. Most of its length is over reclamation of the foreshore or
within cuttings through the rugged coastline. On the other hand, the Route 3 (Tsing Yi & Kwai Chung
Sections) and the West Kowloon Expressway are mostly on viaducts. The tricky parts are the viaducts over
the existing roads and sea channel.
In order not to disturb existing traffic underneath, the viaducts were
constructed by employing specialized technique. Photos of the roads at grade or on viaduct are shown below.
|
|
|
North Lantau Expressway |
|
|
|
|
|
Route 3 (Tsing Yi & Kwai Chung Sections) |
|
|
|
|
|
West Kowloon Expressway |
More details of the various projects
are given by clicking on the appropriate projects in the layout plan under the
section ¡§PROJECT SCOPE¡¨ above.
The construction periods for the
various projects are tabulated below:
|
Project |
Construction start |
Construction end |
|
Western
Harbour Crossing |
1993 |
1997 |
|
West
Kowloon Expressway |
1993 |
1997 |
|
Route 3
(Kwai Chung & Tsing Yi Sections) |
1993 |
1997 |
|
Lantau
Link |
1992 |
1997 |
|
North
Lantau Expressway |
1992 |
1997 |
|
Ting Kau
Bridge |
1995 |
1998 |
|
Route 3 (Country Park Section) |
1995 |
1998 |
It can be seen that the expressways
falling under the ACP categories were completed in year 1997, in line with the
wish expressed in the decision made in year 1989.
The successfulness to complete ACP
expressway projects on time relied heavily on the ability of the project
management staff. Basically,
day-to-day management was in the hands of the project management offices within
the Highways Department of the Hong Kong Government. Because of the importance of the ACP projects, the programme
was monitored by special organizations set up within the government, which
included the New Airport Works Coordination Office (NAPCO) and the Airport
Development Steering Committee (ADSCOM) who was assisted by a standing
executive committee Subcommittee, Airport Core Programme (SCACP).
The Hierarchy is as follows and
respective roles of the above organizations as shown:
|
ADSCOM Resolved and
decided on significant policy issues and matters affecting more than one
policy branches within the government |
â
|
SCACP Monitored and resolved all technical works-related problems that could not be resolved at lower levels, and referred unresolved issues to ADSCOM |
â
|
NAPCO Served as an executive arm of ADSCOM in monitoring status, giving guidance, resolving cross-department issues, and referring difficult problems, where necessary, to ADSCOM |
â
|
Project Management Office, Highways Department Day-to-day
management of ACP expressway projects |
For the two non-ACP projects, the
Ting Kau Bridge and the Route 3 (Country Park Section), project management was
basically carried out within the Project Management Offices and their works
monitored by the Highways Department.
In order to complete the projects on
time, works related to design and construction were done through
outsourcing. Open, fair tender
system was adopted to ensure that the best mix of expertise around the world be
available to carry out the various activities.
The contract awards reflect the international nature of the ACP.
People's Republic of China had gained the largest share (by value) with 31%
(Hong Kong 23%, Mainland 8%) followed by: Japan (26%), UK (16%), the
Netherlands (6%), France (5%), Belgium (3%), New Zealand (3%), Spain (2%),
Australia (2%), the United States (2%), Germany(2%) and others (including
Italy, South Africa, Sweden, Austria, Norway, Portugal and Denmark) (2%).
The total number of passengers using the Hong Kong
International Airport last year reached a record high of 32 million passengers
per year. It demonstrates the
importance of the decision made back in year 1989 to build the new
airport. The initial phase of the
airport has a capacity of 35 million passengers per year, and as China is about
to join the World Trade Organization, it is expected that Hong Kong, being the
hub of a network of air transport services to China, will continue to grow in
the number of air passengers. As
such, even the new airport will have to be further developed. In fact, with the second runway already
completed, and after phased completion of the supporting facilities, the
airport at Chek Lap Kok can handle up to 87 million passengers per year.
|
|
|
Chek Lap Kok Hong Kong
International Airport |
Correspondingly, there are new road networks under
plan to meet the future demand along the airport expressway corridor. Route 9 between Tsing Yi and Sha Tin
and Route 10 between north Lantau and northwest New Territories are being
implemented to fulfil this need.
For details of these two future roads, please visit the following web
site: http://www.hyd.gov.hk/.